Nuclear restarts, new builds and fuel supply, with every date sourced.
NuclearTelemetry follows nuclear restarts, new builds and the plants behind power agreements with hyperscalers, data center companies and utilities, together with the dated record of enrichment and fuel contracts. Every date is attributed to the party that stated it and links to its source. Dates stated by a company are the company's, not ours.
Which nuclear restarts and new builds have dates on the record, who has committed to buy the power, and is the fuel there to run them?
Projects
Name, owner, location and reactor type for each restart, new build and plant tracked, with the target date as the company states it, named as the company's and linked to its source.
Commitments
Power agreements and other commitments between nuclear projects and buyers such as hyperscalers, data center companies and utilities, with the counterparty and the date announced.
Fuel supply
Enrichment and fuel contracts, laws, waivers and capacity, in date order, each linked to its source.
On screen with a trial
Announced date against the current date for each project, who buys the power, and the fuel supply timeline. A date from a secondary source is marked as such.
Used by utilities, power buyers, lenders and energy investors.
What is in the record
18
projects and plants: restarts, new builds and plants with power agreements
12
commitments: power agreements and other agreements between nuclear projects and buyers such as hyperscalers, data center companies and utilities
19
dated fuel supply events: enrichment and fuel contracts, laws, waivers and capacity
Counts are read from our data and refreshed about once an hour. They count records, not megawatts, and say nothing about which projects will finish or when.
Dates here are the company’s, not ours
On this public page, a project date appears only as the company states it, marked “Company says”, with the name of the source and a link to it. We make no call of our own on how a project is progressing or whether it is meeting its schedule. Nothing here is an approval or a forecast, and it says nothing about regulatory approval beyond what a linked source itself states. Not investment advice and not a credit rating.
| Project | Owner | Location | Reactor | Company says |
|---|---|---|---|---|
| Amazon / X-energy Xe-100 program, Energy Northwest project | X-energy and Energy Northwest (project); Amazon (investor and customer) | Central Washington | Xe-100 | Company says: Operations targeted for the 2030s Stated Oct 23, 2025. Source: Energy Northwest |
| Clinton Clean Energy Center, power purchase agreement with Meta | Constellation Energy | Clinton, Illinois | Company says: Beginning in June of 2027 (power purchase agreement) Power purchase agreement: an agreement under which a buyer purchases electricity from the plant on agreed terms. Stated Jun 3, 2025. Source: Constellation Energy | |
| Crane Clean Energy Center (Three Mile Island Unit 1) restart | Constellation Energy | Londonderry Township, Pennsylvania | Company says: Restarting operations in 2027 Stated Aug 6, 2026. Source: Constellation Energy | |
| Darlington New Nuclear Project, Unit 1 (BWRX-300) | Ontario Power Generation | Darlington, Ontario, Canada | BWRX-300 | Company says: By the end of 2030 Stated May 8, 2025. Source: Ontario Power Generation |
| Duane Arnold Energy Center restart | NextEra Energy | Palo, Iowa | Company says: No later than the first quarter of 2029 Stated Oct 21, 2026. Source: NextEra Energy | |
| Holtec SMR-300 Pioneer 1 and 2, Palisades site | Holtec | Covert, Michigan | SMR-300 | Company says: Expected to be commissioned in the early 2030s (Holtec S-1/A, Sep 8, 2026; that registration was withdrawn Sep 25, 2026) Stated Sep 8, 2026. Source: Holtec Nuclear Corp |
| Kairos Power / Google advanced reactor fleet (500 MW) | Kairos Power | United States; sites not stated in the release | Company says: First deployment by 2030; 500 MW fleet by 2035 Stated Oct 14, 2024. Source: Kairos Power | |
| Kairos Power Hermes 2 | Kairos Power | Oak Ridge, Tennessee | KP-FHR | Company says: Scheduled to begin operations in 2030 Stated Aug 18, 2025. Source: Kairos Power |
| Oklo Aurora powerhouses, Pike County Ohio campus (Meta) | Oklo | Pike County, Ohio | Aurora | Company says: First phase targeted to come online as early as 2030 Date of statement not shown on the source. Source: Oklo |
| Oklo Aurora-INL powerhouse | Oklo | Idaho National Laboratory, Idaho | Aurora | Company says: Ambitious target of deploying our first powerhouse in 2028-2029 Stated Nov 6, 2026. Source: Oklo Inc. Form 10-Q (quarter ended Sep 30, 2026) |
| Palisades Nuclear Plant restart | Holtec | Covert, Michigan | Company says: Holtec said on Sep 8, 2026 that it expected to restart in 2026 (Holtec S-1/A); that registration was withdrawn Sep 25, 2026 Stated Sep 8, 2026. Source: Holtec Nuclear Corp | |
| Susquehanna nuclear plant, power purchase agreement with Amazon | Talen Energy | Pennsylvania | Company says: Power deliveries to Amazon ramp up to the full 1,920 MW no later than 2032 Power purchase agreement: an agreement under which a buyer purchases electricity from the plant on agreed terms. Stated Jun 11, 2025. Source: Talen Energy | |
| TerraPower Natrium plants for Meta (up to 8 units, sites not chosen) | TerraPower | United States; first dual-unit site not yet selected | Natrium | Company says: Delivery of initial units as early as 2032 Stated Jan 9, 2026. Source: TerraPower |
| TerraPower Natrium, Kemmerer Unit 1 | TerraPower | Kemmerer, Lincoln County, Wyoming | Natrium | Company says: Expected to be completed in 2030 Stated Mar 4, 2026. Source: TerraPower |
| Vistra nuclear plants (Perry, Davis-Besse, Beaver Valley), power purchase agreements with Meta | Vistra | Ohio and Pennsylvania | Company says: Meta purchases start late 2026; contracted volume of 2,609 MW, including 433 MW of uprates, reaches full level in 2034 Power purchase agreement: an agreement under which a buyer purchases electricity from the plant on agreed terms. Stated Jan 9, 2026. Source: Vistra |
Some statements are older than others. A project is listed only where the company itself states a date, so this list is not every nuclear project.
How it is sourced
Primary sources first
Company news releases and filings, SEC filings, and documents from regulators and agencies such as the NRC, the Federal Register, the DOE and Canada’s CNSC.
Each date has an owner
A date is attributed to whoever stated it. If only a trade publication reports a date, the app marks it as a secondary source and never presents it as the company’s.
Checked and dated
Each record shows the day it was last checked. Where no date has been found, the app says so instead of filling the gap.
What is free and what a 7-day trial adds
Free, no account
This page: what NuclearTelemetry tracks, the counts above and how it is sourced.
Free 7-day trial, no card
The NuclearTelemetry pages on screen: for each project, the date first announced and the current date with the change in months, who buys the power, the dated fuel supply timeline and the sources behind each record. Trials have no file downloads.
Part of the West Orange Labs platform.
One sign-in covers every product, and records link across them.
PreciousTelemetry
What buyers report paying for scrap gold, silver, platinum and palladium.
About PreciousTelemetryTry NuclearTelemetry free for 7 days.
Create an account and use it now, with no card needed. Or tell us what you are looking into and we will write back.