ChipTelemetry

Tracked, not assessed

25 financings of AI data centers and AI-cloud companies, $39.3 billion in dollars plus €2.0 billion in euros, as of Nov 9, 2026. We follow them. We have not given them a Financing Condition Report.

What this page is

These are financings we read about in primary public sources: filings with the SEC and the companies' own releases. We list the borrower, the amount, the kind of debt, the date, and the lenders or banks the source names. We have not assessed any of them. None has a Financing Condition Report, and no line here says anything about whether a borrower is likely to repay.

A Financing Condition Report is a separate, narrower thing. It records what a facility's own filings disclose about its loan terms, as of a date, and carries a signed certificate. It is not a credit rating. Most of the debt below is secured by data center property or by the company's assets, not by AI chips, and the securitizations are not backed by chips at all.

How to read the amounts. Each amount is the size stated in the source on the date shown: notes issued, a loan or credit line committed. It is not the balance owed today. Credit lines are commitments and may be undrawn. Euro amounts are shown in euros and are not added to the dollar totals. Lines can be repaid, refinanced or amended after the date shown.

Totals

  • Data center project debt12 lines, $27,130M
  • Corporate credit of AI-cloud and data center companies11 lines, $10,600M plus €2,000M
  • Data center securitizations2 lines, $1,568M
  • All tracked, not assessed25 lines, $39,298M ($39.3 billion) plus €2,000M

Data center project debt

Notes and loans raised for a specific data center campus or project company.

  • Hut 8 (Hut 8 DC LLC), River Bend campus, Louisiana: $3,250M6.192% senior secured notes due 2042Named in the source: Initial purchasers led by J.P. Morgan Securities; trustee Wilmington TrustSource type: SEC Form 8-K, April 2026. Financing Condition Report: none, not assessed.
  • Hut 8 (Beacon Point DC LLC), Nueces County, Texas: $4,250M6.129% senior secured notes due 2042Named in the source: Initial purchasers led by J.P. Morgan Securities; trustee Wilmington TrustSource type: SEC Form 8-K, June 2026. Financing Condition Report: none, not assessed.
  • Core Scientific (Core Scientific Finance I LLC): $3,300M7.750% senior secured notes due 2031Named in the source: Initial purchasers led by Morgan Stanley and J.P. Morgan SecuritiesSource type: SEC Form 8-K, April and May 2026. Financing Condition Report: none, not assessed.
  • Cipher (Cipher Compute LLC), Barber Lake, Texas: $1,733M7.125% senior secured notes due 2030 ($1,400M closed Nov 13, 2025 plus $333M added Nov 24, 2025)Named in the source: Morgan Stanley (initial purchaser); trustee Wilmington TrustSource type: SEC Form 8-K, November 2025. Financing Condition Report: none, not assessed.
  • Cipher (Black Pearl Compute LLC), Wink, Texas: $2,000M6.125% senior secured notes due 2031Named in the source: Morgan Stanley (representative of the initial purchasers); trustee Wilmington TrustSource type: SEC Form 8-K, February 2026. Financing Condition Report: none, not assessed.
  • Cipher (Stingray Compute LLC), Andrews, Texas: $810M6.000% senior secured notes due 2031Named in the source: Morgan Stanley (representative of the initial purchasers); trustee Wilmington TrustSource type: SEC Form 8-K, June 2026. Financing Condition Report: none, not assessed.
  • Applied Digital (APLD ComputeCo LLC), Ellendale, North Dakota: $2,350M9.250% senior secured notes due 2030Named in the source: Initial purchasers not named in the filings we readSource type: Company release, November 2025. Financing Condition Report: none, not assessed.
  • Applied Digital (APLD ComputeCo 2 LLC), Harwood, North Dakota: $2,150M6.750% senior secured notes due 2031Named in the source: Initial purchasers not named in the filings we readSource type: SEC Form 8-K, March 2026. Financing Condition Report: none, not assessed.
  • Applied Digital (APLD ComputeCo 3 LLC), Ellendale, North Dakota: $1,590M7.000% senior secured notes due 2031Named in the source: Initial purchasers not named in the filings we readSource type: SEC Form 8-K, June 2026. Financing Condition Report: none, not assessed.
  • Galaxy Digital (Galaxy Helios I LLC), Helios campus, Texas: $1,400MSenior secured term loan maturing August 2028Named in the source: Deutsche Bank AG New York Branch (initial lender); GLAS USA (administrative and collateral agent)Source type: SEC Form 8-K, August 2025. Financing Condition Report: none, not assessed.
  • Galaxy Digital (Galaxy Helios Data Centers II LLC), Helios Phase II: $3,507M9.875% senior secured notes due 2031Named in the source: Initial purchasers not named in the filings we readSource type: SEC Form 8-K, July 2026. Financing Condition Report: none, not assessed.
  • Nscale, Narvik data center, Norway: $790MCommitted data center financing, plus a separate $790M uncommitted expansion optionNamed in the source: ABN AMRO, DNB, Nordea, Eksfin and SEBSource type: Company release, May 2026. Financing Condition Report: none, not assessed.In our Financing Condition Report record: Nscale: 6 loans secured by AI chips.

Corporate credit of AI-cloud and data center companies

Revolving credit facilities, credit lines and unsecured notes raised by the company itself. Credit lines are commitments, not amounts drawn.

  • Hut 8 Corp.: $1,070MFour-year senior secured revolving credit facility; nothing drawn at closeNamed in the source: JPMorgan Chase Bank (administrative and collateral agent)Source type: SEC Form 8-K, September 2026. Financing Condition Report: none, not assessed.
  • Core Scientific, Inc.: $600M$100M revolving facility plus $500M letter-of-credit facility, senior secured; undrawn at closeNamed in the source: JPMorgan Chase Bank (administrative and collateral agent)Source type: SEC Form 8-K, August 2026. Financing Condition Report: none, not assessed.
  • TeraWulf Inc.: $400MSenior secured revolving credit facility, about $400M after an October 23, 2026 amendment (first signed May 7, 2026 at $250M)Named in the source: Morgan Stanley Senior Funding (agent); Santander, Bank of America, Citi, Citizens, SMBC, TD and Wells Fargo as arrangersSource type: SEC Form 8-K, October 2026. Financing Condition Report: none, not assessed.
  • Cipher Digital Inc.: $200MFour-year senior secured revolving credit facility; undrawnNamed in the source: Morgan Stanley Senior Funding (agent); Santander, Goldman Sachs Lending Partners, JPMorgan, SMBC and Wells Fargo as arrangersSource type: SEC Form 8-K, March 2026. Financing Condition Report: none, not assessed.
  • Applied Digital (APLD Intermediate HoldCo LLC): $430MSecured revolving credit facility, raised from $350M to $430M on June 26, 2026Named in the source: First National Bank of Omaha (agent); Goldman Sachs Lending Partners; Mizuho, RBC, Santander and Wells FargoSource type: SEC Form 8-K, June 2026. Financing Condition Report: none, not assessed.
  • Lambda: $1,000MMulti-tranche syndicated senior secured credit facilityNamed in the source: J.P. Morgan (lead arranger); other lenders not namedSource type: Company release, May 2026. Financing Condition Report: none, not assessed.In our Financing Condition Report record: Lambda: 3 loans secured by AI chips.
  • Nscale Limited: $900MRevolving credit facilityNamed in the source: J.P. Morgan, Goldman Sachs, Morgan Stanley, MUFG, RBC Capital Markets, Bank of America, Crédit Agricole CIB, Deutsche Bank, Mizuho, SMBC, TD Securities and KeyBankSource type: Company release, July 2026. Financing Condition Report: none, not assessed.In our Financing Condition Report record: Nscale: 6 loans secured by AI chips.
  • Vantage Data Centers: $2,000MFive-year revolving development and warehouse credit facilityNamed in the source: Evercore and Wells Fargo Securities (lead arrangers); about a dozen insurance and institutional lenders not namedSource type: Company release, September 2026. Financing Condition Report: none, not assessed.
  • CoreWeave, Inc.: $2,750M9.750% senior unsecured notes due 2031 ($1,750M on April 14, 2026 plus $1,000M added April 21, 2026)Named in the source: Initial purchasers not named; trustee U.S. Bank Trust CompanySource type: SEC Form 8-K, April 2026. Financing Condition Report: none, not assessed.In our Financing Condition Report record: CoreWeave: 7 loans secured by AI chips.
  • CoreWeave, Inc.: $1,250M9.625% senior unsecured notes due 2032Named in the source: Initial purchasers not named; trustee U.S. Bank Trust CompanySource type: SEC Form 8-K, June 2026. Financing Condition Report: none, not assessed.In our Financing Condition Report record: CoreWeave: 7 loans secured by AI chips.
  • CoreWeave, Inc.: €2,000M8.500% senior unsecured notes due 2032, issued in eurosNamed in the source: Initial purchasers not named; trustee U.S. Bank Trust CompanySource type: SEC Form 8-K, June 2026. Financing Condition Report: none, not assessed.In our Financing Condition Report record: CoreWeave: 7 loans secured by AI chips.

Data center securitizations

Notes backed by pools of leased data centers. These are not backed by AI chips.

  • Switch, Series 2026-1 data center securitization: $768MGreen data center ABS notes, about $768M, adding a Reno, Nevada data center to a pool of 11Named in the source: Barclays and Citigroup (structuring advisors); BMO and Truist (bookrunners)Source type: Company release, April 2026. Financing Condition Report: none, not assessed.
  • Flexential, data center securitization: $800MGreen ABS term notes under its master trust (sixth and seventh series)Named in the source: Investors not namedSource type: Company release, November 2025. Financing Condition Report: none, not assessed.

This list is not complete. It holds only financings we have read in a primary source and could confirm; reports we could not confirm are left out. We add lines as we confirm them and note changes in the update log. A line may move to a Financing Condition Report only if its own filings give us evidence to assess. To follow these financings, start the free trial.

Not a credit rating and not investment advice. Lenders · Loans secured by AI chips · Financing Condition Reports · Update log · When tracked debt comes due · Follow changes (RSS)

Loans that do carry a Financing Condition Report

The Financing Condition Report pages list each loan with a result, the as-of date and a signed certificate you can check in your browser. The lines on this page have none of these.

One short email a week. We use your address only for this, and you can unsubscribe in one click.

Data on this site is provided for personal, non-commercial reading. Automated collection, bulk copying and redistribution are not permitted without a written license. See the Terms. The machine-readable files listed on the Data and license page are the exception and may be reused under CC BY 4.0.

Not investment advice. Figures come from public filings and published price lists. Read the weekly brief · Plain-English explainers