Texas: rules for data centers and large power customers

7 rules tracked in Texas. Each sets what a large new customer must commit to in order to connect.

Rules we track in Texas

AEP Texas
PUCT Project No. 58481 (statewide large load interconnection rule) (approved)
CenterPoint Energy Houston Electric
PUCT Project No. 58481 (statewide large load interconnection rule) (approved)
El Paso Electric
PUCT Docket 59076 (pending)
Oncor Electric Delivery
PUCT Project No. 58481 (statewide large load interconnection rule) (approved)
Southwestern Electric Power Company (AEP)
PUCT Docket 58796 (pending)
Southwestern Public Service (Xcel Energy, Texas)
(proposed)
Texas statewide rule (SB 6)
PUCT Project No. 58481 (approved)

All states

See the terms behind each rule

Subscribers see the minimum contract length, ramp, minimum bill, exit terms and collateral, each linked to the order or statute.

Not investment advice. Figures come from public filings. Read the weekly brief